Silver Dollar Solar
BetaActiveSolarERCOTLBNL + Live
301.9 MW generation in Freestone, TX · In queue since June 2024 · Proposed COD April 2028
301.9 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 10m
Facilities Study50%
Queue EntryJun 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-28
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Silver Dollar Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV Big Brown 3380 to Navarro 68091 ckt#2
Data Source
LBNL + Live