Trenno BESS
ERCOT-27INR0173BetaActiveBatteryERCOTLBNL + Live
202.56 MW storage in Johnson, TX · In queue since February 2024 · Proposed COD September 2027
202.56 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Facilities Study50%
Queue EntryFeb 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-13
Project Details
State
TX
County
Johnson
Region
ERCOT
Developer
JSB1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 2281 Godley - 2888 Carmichael
Data Source
LBNL + Live
No news available for this project.