New Shepherd Solar
BetaActiveSolarERCOTLBNL + Live
150.81 MW generation in Karnes, TX · In queue since January 2024 · Proposed COD September 2029
150.81 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryJan 11, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-30
Project Details
State
TX
County
Karnes
Region
ERCOT
Developer
New Shepherd Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
the Kenedy Switching Station #2 (#8186) _x0013_ Rosata POD (#8153) line, AEP.
Data Source
LBNL + Live
No news available for this project.