Coyote Den Storage
BetaActiveBatteryERCOTLBNL + Live
156.61 MW storage in Karnes, TX · In queue since February 2024 · Proposed COD September 2029
156.61 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryFeb 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-30
Project Details
State
TX
County
Karnes
Region
ERCOT
Developer
Coyote Den Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
The Kenedy Switching Station #2 (#8186) to Rosata POD (#8153) Line ; AEP
Data Source
LBNL + Live
No news available for this project.