Bluefox Solar 1
BetaActiveSolarERCOTLBNL + Live
402.6 MW generation in Matagorda, TX · In queue since March 2024 · Proposed COD May 2029
402.6 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 2m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Industrial November Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
#8754 Zoisite 345kV
Data Source
LBNL + Live
No news available for this project.