RedSun Solar
ERCOT-27INR0124BetaActiveSolarERCOTLBNL + Live
82.55 MW generation in Burnet, TX · In queue since December 2023 · Proposed COD August 2028
82.55 MW
Capacity
1
Components
Solar
2y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntryDec 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-28
Project Details
State
TX
County
Burnet
Region
ERCOT
Developer
Gransolar Texas Twenty Two
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7100 Burnet - 7529 Bertram
Data Source
LBNL + Live
No news available for this project.