Grapefruit Solar — Project Summary

Queue ID
ERCOT-27INR0118
Capacity
301.2 MW
Technology
Solar
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
Grapefruit Solar LLC
IA Status
Facility Study

Grapefruit Solar

ERCOT-27INR0118BetaActiveSolarERCOTLBNL + Live

301.2 MW generation in Hidalgo, TX · In queue since February 2024 · Proposed COD December 2028

301.2 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 10m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

TX

County

Hidalgo

Region

ERCOT

Developer

Grapefruit Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

North Edinburg (Bus #8905) - Reforzar (Bus # 80078) 345kV

Data Source

LBNL + Live

No news available for this project.