Menarcho
BetaActiveWindERCOTLBNL + Live
405.4 MW generation in Concho, TX · In queue since January 2024 · Proposed COD October 2028
405.4 MW
Capacity
1
Components
Wind
2y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntryJan 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-01
Project Details
State
TX
County
Concho
Region
ERCOT
Developer
Orsted Onshore Development North America, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345-kV Double Circuit Amos Creek (7077) _x0013_ Brown (1444)/Amos Creek (7077) _x0013_ Bow Wood (76006)
Data Source
LBNL + Live
No news available for this project.