Starlight Solar
ERCOT-27INR0105BetaActiveSolarERCOTLBNL + Live
130.72 MW generation in Mills, TX · In queue since February 2024 · Proposed COD May 2030
130.72 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 3m
Facilities Study50%
Queue EntryFeb 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-05-09
Project Details
State
TX
County
Mills
Region
ERCOT
Developer
Mills Tx Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap the 138 kV Goldthwaite (#7070) _x0013_ San Saba Switch (#77074)
Data Source
LBNL + Live
No news available for this project.