Starlight Solar — Project Summary

Queue ID
ERCOT-27INR0105
Capacity
130.72 MW
Technology
Solar
Status
active
Location
Mills, TX
Region
ERCOT
Developer
Mills Tx Solar LLC
IA Status
Facility Study

Starlight Solar

ERCOT-27INR0105BetaActiveSolarERCOTLBNL + Live

130.72 MW generation in Mills, TX · In queue since February 2024 · Proposed COD May 2030

130.72 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 3m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-05-09

Project Details

State

TX

County

Mills

Region

ERCOT

Developer

Mills Tx Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap the 138 kV Goldthwaite (#7070) _x0013_ San Saba Switch (#77074)

Data Source

LBNL + Live

No news available for this project.