JUNIPERUS BESS
BetaActiveBatteryERCOTLBNL + Live
226.39 MW storage in Hopkins, TX · In queue since October 2023 · Proposed COD July 2029
226.39 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryOct 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-09
Project Details
State
TX
County
Hopkins
Region
ERCOT
Developer
BLUE STONE RENEWABLE XXI LLC
Utility
—
Entity
ERCOT
Point of Interconnection
TAP CASHSW_T5 (2464) -SULSP_SS1_5 (1697)
Data Source
LBNL + Live
No news available for this project.