Guadalupe Battery Storage Project
BetaActiveBatteryERCOTLBNL + Live
210.5 MW storage in Guadalupe, TX · In queue since November 2023 · Proposed COD May 2027
210.5 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntryNov 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
TX
County
Guadalupe
Region
ERCOT
Developer
Guadalupe Power Partners, LP
Utility
—
Entity
ERCOT
Point of Interconnection
# 7044 Marion 345kV
Data Source
LBNL + Live
No news available for this project.