Tumbleweed Solar
BetaActiveSolarERCOTLBNL + Live
613.89 MW generation in Borden, TX · In queue since September 2023 · Proposed COD December 2027
613.89 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntrySep 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
Hecate Energy Tumbleweed Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
59905 Faraday 345 kV
Data Source
LBNL + Live
No news available for this project.