Eagle Claw Energy Center
ERCOT-27INR0085BetaActiveBatteryERCOTLBNL + Live
200.84 MW storage in Grimes, TX · In queue since October 2023 · Proposed COD March 2028
200.84 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryOct 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-31
Project Details
State
TX
County
Grimes
Region
ERCOT
Developer
Cypress Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
30.615932, -95.962023 - Singleton (Bus #44645) - Zenith (Bus #44900) Circuit #98 345 kV Line
Data Source
LBNL + Live