Orbit Energy Storage
BetaActiveBatteryERCOTLBNL + Live
501.94 MW storage in Bexar, TX · In queue since November 2023 · Proposed COD June 2027
501.94 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Facilities Study50%
Queue EntryNov 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
GCI Orbit Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV Calaveras Power Station (BUS #5400) to HOWARD_5 (BUS #5231).
Data Source
LBNL + Live
No news available for this project.