200.8 MW storage in Pecos, TX · In queue since September 2023 · Proposed COD January 2027
200.8 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Facilities Study50%
Queue EntrySep 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-31
Project Details
State
TX
County
Pecos
Region
ERCOT
Developer
Laurel Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 60404 Solstice - 76002 Bakersfield Ckt 2