Lili Wind
ERCOT-27INR0076BetaActiveWindERCOTLBNL + Live
240 MW generation in Sterling, TX · In queue since January 2024 · Proposed COD July 2028
240 MW
Capacity
1
Components
Wind
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryJan 11, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Sterling
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Sand Bluff <59902> Divide <76090>, 345kV
Data Source
LBNL + Live
No news available for this project.