Supra Wind
BetaActiveWindERCOTLBNL + Live
205.86 MW generation in Hardeman, TX · In queue since July 2023 · Proposed COD December 2027
205.86 MW
Capacity
1
Components
Wind
2y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 5m
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-23
Project Details
State
TX
County
Hardeman
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap #6101 Riley 7A to #60505 Edithcla 7B 345kV
Data Source
LBNL + Live
No news available for this project.