Panhandle Flagship Solar 2
304.4 MW generation in Hutchinson, TX · In queue since March 2023 · Proposed COD June 2031
304.4 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2031
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-30
State
TX
County
Hutchinson
Region
ERCOT
Developer
Panhandle Solar Group Operating Company LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Railhead Substation (RAILHEAD #79005). Station 2 (27INR0023) connects to Station 1 (27INR0022 & 27INR0025)via a 4.9 mile internal tie line. Station 1 (27INR0022 & 27INR0025) connects to POIB via 22.5 mile tie-line
Data Source
LBNL + Live