Live Oak Bayou Solar SLF
BetaActiveSolarERCOTLBNL
156.06 MW generation in Matagorda, TX · In queue since May 2023 · Proposed COD December 2027
156.06 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
FRESH AIR ENERGY II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV Refuge (42400) - Hawkinsville (42440) ckt 27
Data Source
LBNL
No news available for this project.