Kit Fox Storage
BetaActiveBatteryERCOTLBNL + Live
153.6 MW storage in Henderson, TX · In queue since March 2023 · Proposed COD July 2027
153.6 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
Facilities Study50%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Henderson
Region
ERCOT
Developer
Kit Fox Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Walton Switch (6899) 138KV
Data Source
LBNL + Live
No news available for this project.