Dundee South B Wind
ERCOT-27INR0011BetaActiveWindERCOTLBNL + Live
300.27 MW generation in Baylor, TX · In queue since January 2023 · Proposed COD December 2027
300.27 MW
Capacity
1
Components
Wind
3y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryJan 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Baylor
Region
ERCOT
Developer
Felix 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Riley Substation (#6101); AEP
Data Source
LBNL + Live
No news available for this project.