Puerto Del Sol 2
BetaActiveSolarERCOTLBNL + Live
213.8 MW generation in Cameron, TX · In queue since May 2022 · Proposed COD December 2027
213.8 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryMay 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Cameron
Region
ERCOT
Developer
PUERTO DEL SOL, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1
Data Source
LBNL + Live