Zeus Mitchell BESS II — Project Summary

Queue ID
ERCOT-26INR0686
Capacity
1042.94 MW
Technology
Battery
Status
active
Location
Mitchell, Texas
Region
ERCOT
Developer
Zeus Mitchell BESS II, LLC
IA Status

Zeus Mitchell BESS II

BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT

1,042.94 MW storage in Mitchell, Texas · In queue since June 2025 · Proposed COD May 2027

1,042.94 MW

Capacity

0

Components

9 months

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

1y 11m

Pre-Study0%
Queue EntryJun 19, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-01

Project Details

State

Texas

County

Mitchell

Region

ERCOT

Developer

Zeus Mitchell BESS II, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02

Data Source

Live · ERCOT

No news available for this project.