Exergy Energy West Texas Natural Gas Reciprocating Power I
BetaActiveGas - Internal CombustionERCOTLive · ERCOT
400 MW generation in Reeves, Texas · In queue since July 2025 · Proposed COD May 2027
400 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
1y 10m
Pre-Study0%
Queue EntryJul 22, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
Texas
County
Reeves
Region
ERCOT
Developer
August Partners LLC
Utility
—
Entity
ERCOT
Point of Interconnection
38095 TNJACKRBT1 138kV
Data Source
Live · ERCOT
No news available for this project.