Amberjack2 BESS — Project Summary

Queue ID
ERCOT-26INR0640
Capacity
180 MW
Technology
Battery
Status
active
Location
Cameron, Texas
Region
ERCOT
Developer
Hunt Energy Network, LLC
IA Status

Amberjack2 BESS

BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT

180 MW storage in Cameron, Texas · In queue since January 2025 · Proposed COD March 2027

180 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 2m

Pre-Study0%
Queue EntryJan 28, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-08

Project Details

State

Texas

County

Cameron

Region

ERCOT

Developer

Hunt Energy Network, LLC

Utility

Entity

ERCOT

Point of Interconnection

79501 KINGFISHER 345KV

Data Source

Live · ERCOT

No news available for this project.