Amberjack2 BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
180 MW storage in Cameron, Texas · In queue since January 2025 · Proposed COD March 2027
180 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 2m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-08
Project Details
State
Texas
County
Cameron
Region
ERCOT
Developer
Hunt Energy Network, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
79501 KINGFISHER 345KV
Data Source
Live · ERCOT
No news available for this project.