Lyra Storage
ERCOT-26INR0636BetaActiveOtherBattery Energy StorageERCOTLive · ERCOT
500 MW hybrid in Borden, TX · In queue since May 2025 · Proposed COD November 2026
500 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Signed Aug 2025
Interconnection Timeline
Queue → IA
3 months
IA → COD
1y 3m
Total Duration
3 months
Construction0%
Queue EntryMay 27, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 13, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-11-12
Project Details
State
TX
County
Borden
Region
ERCOT
Developer
JUNO BESS I
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV MULESHOE (#59922)
Data Source
Live · ERCOT