Betel Storage II
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
500 MW storage in Milam, Texas · In queue since January 2025 · Proposed COD December 2026
500 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 11m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-17
Project Details
State
Texas
County
Milam
Region
ERCOT
Developer
BETEL STORAGE II
Utility
—
Entity
ERCOT
Point of Interconnection
3377 Little Pond 345
Data Source
Live · ERCOT
No news available for this project.