Buffalo Gap 3 Wind Repower
ERCOT-26INR0626BetaActiveWindERCOTLBNL + Live
168.63 MW generation in Taylor, TX · In queue since December 2024 · Proposed COD February 2027
168.63 MW
Capacity
1
Components
Wind
1y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 2m
Facilities Study50%
Queue EntryDec 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
TX
County
Taylor
Region
ERCOT
Developer
Buffalo Gap Wind Farm 3, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6216 Bluff_Creek 138kV
Data Source
LBNL + Live
No news available for this project.