Buffalo Gap 2 Wind Repower
ERCOT-26INR0625BetaActiveWindERCOTLBNL + Live
231.81 MW generation in Nolan, TX · In queue since December 2024 · Proposed COD February 2027
231.81 MW
Capacity
1
Components
Wind
1y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 2m
Facilities Study50%
Queue EntryDec 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
TX
County
Nolan
Region
ERCOT
Developer
Buffalo Gap Wind Farm 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6216 Bluff Creek 138 kV
Data Source
LBNL + Live
Linked EIA Plant
Buffalo Gap 2 Wind Farm
EIA Plant ID: 56484