White Bright BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
313.69 MW storage in Grayson, Texas · In queue since March 2025 · Proposed COD April 2029
313.69 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 1m
Pre-Study0%
Queue EntryMar 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-16
Project Details
State
Texas
County
Grayson
Region
ERCOT
Developer
VLN, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 1729 Valley South – Anna Switch 2373
Data Source
Live · ERCOT
No news available for this project.