Damia Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
153 MW storage in Eastland, Texas · In queue since April 2025 · Proposed COD July 2028
153 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntryApr 1, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
Texas
County
Eastland
Region
ERCOT
Developer
Damia Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8
Data Source
Live · ERCOT
No news available for this project.