Crocus Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
51 MW storage in Stephens, Texas · In queue since January 2025 · Proposed COD July 2028
51 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
Texas
County
Stephens
Region
ERCOT
Developer
Crocus Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)
Data Source
Live · ERCOT
No news available for this project.