Tennuto BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
202 MW storage in Cooke, Texas · In queue since January 2025 · Proposed COD December 2027
202 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 11m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
Texas
County
Cooke
Region
ERCOT
Developer
Tennuto BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Wolfridge (#730)
Data Source
Live · ERCOT
No news available for this project.