Callisto ID Energy Center
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Harris, TX · In queue since October 2024 · Proposed COD December 2026
100 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 2m
Facilities Study50%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
Tempus Power management LLC
Utility
—
Entity
ERCOT
Point of Interconnection
47150 (H_O_C__B138) 138kV
Data Source
LBNL + Live
No news available for this project.