Pine Forest BESS 2
201.4 MW storage in Hopkins, TX · In queue since December 2024 · Proposed COD October 2026
201.4 MW
Capacity
1
Components
Battery
1y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-29
State
TX
County
Hopkins
Region
ERCOT
Developer
Pine Forest Hybrid II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
new SCRSW substation 12464 (Tap 345kV 1696 Monticello SES - 2514 Allen Switch)
Data Source
LBNL
Deriva Energy And Clearway Energy Complete Agreement For Sale Of 833MWdc Of Operating Solar Projects
Deriva Energy, LLC, a leader in clean power generation, operations, and development, along with its joint venture partner Manulife...
Deriva Energy And Clearway Energy Complete Agreement For Sale Of 833MWdc Of Operating Solar Projects
Deriva Energy, LLC, a leader in clean power generation, operations, and development, along with its joint venture partner Manulife...
Deriva Energy And Clearway Energy Complete Agreement For Sale Of 833MWdc Of Operating Solar Projects
Deriva Energy, LLC, a leader in clean power generation, operations, and development, along with its joint venture partner Manulife...
Deriva Energy And Clearway Energy Complete Agreement For Sale Of 833MWdc Of Operating Solar Projects
Deriva Energy, LLC, a leader in clean power generation, operations, and development, along with its joint venture partner Manulife...
Last updated 2026-03-26