ELTEX Power Station — Project Summary

Queue ID
ERCOT-26INR0566
Capacity
487.72 MW
Technology
Gas
Status
active
Location
Austin, TX
Region
ERCOT
Developer
ELTEX Power Station LLC
IA Status
Facility Study

ELTEX Power Station

BetaActiveGasERCOTLBNL

487.72 MW generation in Austin, TX · In queue since September 2024 · Proposed COD June 2027

487.72 MW

Capacity

1

Components

Gas

1y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 9m

Facilities Study50%
Queue EntrySep 4, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

TX

County

Austin

Region

ERCOT

Developer

ELTEX Power Station LLC

Utility

Entity

ERCOT

Point of Interconnection

46220 Peters Substation 138 kV

Data Source

LBNL

No news available for this project.