Fort Worth Power Core Bastrop Gas Plant
BetaActiveGas - Combined-CycleERCOTLive · ERCOT
506.38 MW generation in Bastrop, Texas · In queue since May 2025 · Proposed COD September 2029
506.38 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryMay 27, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-28
Project Details
State
Texas
County
Bastrop
Region
ERCOT
Developer
Fort Worth Power Core LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 7042 ZORN - 7040 AUSTROP
Data Source
Live · ERCOT
No news available for this project.