Coastal Bayou Storage
BetaActiveBatteryERCOTLBNL
174.59 MW storage in Harris, TX · In queue since September 2024 · Proposed COD June 2027
174.59 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 9m
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
TOCE TX BESS 5, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 41690 Hopson - 41700 Warvue
Data Source
LBNL
No news available for this project.