Knight Airport BESS I
BetaActiveBatteryERCOTLBNL + Live
522.46 MW storage in Harris, TX · In queue since August 2024 · Proposed COD October 2027
522.46 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Facilities Study50%
Queue EntryAug 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-15
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
Airport Storage I LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06
Data Source
LBNL + Live
No news available for this project.