Three Canes Solar SLF
ERCOT-26INR0543BetaActiveSolarERCOTLBNL + Live
333 MW generation in Navarro, TX · In queue since July 2024 · Proposed COD July 2027
333 MW
Capacity
1
Components
Solar
1y 9m
In Queue
IA Executed
IA Status
Signed Nov 2024
Interconnection Timeline
Queue → IA
4 months
IA → COD
2y 8m
Total Duration
4 months
Construction75%
Queue EntryJul 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 27, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-31
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Three Canes Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3381 Big Brown _x0013_ 68091 Navarro CKT#02
Data Source
LBNL + Live
No news available for this project.