Longview Wind — Project Summary

Queue ID
ERCOT-26INR0530
Capacity
352.6 MW
Technology
Wind
Status
active
Location
Dawson, TX
Region
ERCOT
Developer
Longview Wind, LLC
IA Status

Longview Wind

ERCOT-26INR0530BetaActiveWindWind TurbineERCOTLive · ERCOT

352.6 MW generation in Dawson, TX · In queue since September 2025 · Proposed COD December 2028

352.6 MW

Capacity

0

Components

7 months

In Queue

IA Status

Signed Dec 2025

Interconnection Timeline

Queue → IA

3 months

IA → COD

3 years

Total Duration

3 months

Construction0%
Queue EntrySep 22, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 16, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Dawson

Region

ERCOT

Developer

Longview Wind, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Venturi (Bus #59923)

Data Source

Live · ERCOT

No news available for this project.