Fagus Solar Park 3 SLF
ERCOT-26INR0524BetaActiveSolarERCOTLBNL + Live
186.83 MW generation in Childress, TX · In queue since June 2024 · Proposed COD May 2027
186.83 MW
Capacity
1
Components
Solar
1y 10m
In Queue
IA Executed
IA Status
Signed Feb 2019
Interconnection Timeline
IA → COD
8y 3m
Total Duration
1y 10m
Construction75%
Queue EntryJun 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 21, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-19
Project Details
State
TX
County
Childress
Region
ERCOT
Developer
Greenalia Solar Power Misae III, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60501 Tesla 345 kV
Data Source
LBNL + Live
No news available for this project.