Millers Branch Solar III
ERCOT-26INR0521BetaActiveSolarERCOTLBNL + Live
133 MW generation in Haskell, TX · In queue since August 2024 · Proposed COD October 2026
133 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 2m
Facilities Study50%
Queue EntryAug 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
TX
County
Haskell
Region
ERCOT
Developer
Miller's Branch Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
BUSS Name: RWMILLER _x0013_ 331 / BUSS Number: 150131-150135
Data Source
LBNL + Live
No news available for this project.