Sky Global West Houston
ERCOT-26INR0519BetaActiveGasERCOTLBNL + Live
324.58 MW generation in Austin, TX · In queue since July 2024 · Proposed COD June 2027
324.58 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 11m
Facilities Study50%
Queue EntryJul 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
TX
County
Austin
Region
ERCOT
Developer
Sky Global Power Two, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 44700 Gebhardt - 44740 Wallis circuit 65
Data Source
LBNL + Live
No news available for this project.