Los Vientos IB Repower — Project Summary

Queue ID
ERCOT-26INR0507
Capacity
184.8 MW
Technology
Wind
Status
active
Location
Willacy, TX
Region
ERCOT
Developer
Los Vientos Windpower IB, LLC
IA Status
Facility Study

Los Vientos IB Repower

BetaActiveWindERCOTLBNL + Live

184.8 MW generation in Willacy, TX · In queue since July 2024 · Proposed COD March 2029

184.8 MW

Capacity

1

Components

Wind

1y 8m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 8m

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Project Details

State

TX

County

Willacy

Region

ERCOT

Developer

Los Vientos Windpower IB, LLC

Utility

Entity

ERCOT

Point of Interconnection

#8319 RIOHONDO 138 kV

Data Source

LBNL + Live

No news available for this project.