Momentum Bock — Project Summary

Queue ID
ERCOT-26INR0506
Capacity
125.38 MW
Technology
Battery
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Momentum Bock, LLC
IA Status
Facility Study

Momentum Bock

BetaActiveBatteryERCOTLBNL + Live

125.38 MW storage in Lamar, TX · In queue since September 2024 · Proposed COD April 2028

125.38 MW

Capacity

1

Components

Battery

1y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 7m

Facilities Study50%
Queue EntrySep 4, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-20

Project Details

State

TX

County

Lamar

Region

ERCOT

Developer

Momentum Bock, LLC

Utility

Entity

ERCOT

Point of Interconnection

1771 LAMAR BLOSSOM 138kV

Data Source

LBNL + Live

No news available for this project.