Goldhill Energy Storage — Project Summary

Queue ID
ERCOT-26INR0505
Capacity
200.58 MW
Technology
Battery
Status
active
Location
Victoria, TX
Region
ERCOT
Developer
Goldhill Energy Storage LLC
IA Status
Facility Study

Goldhill Energy Storage

BetaActiveBatteryERCOTLBNL + Live

200.58 MW storage in Victoria, TX · In queue since April 2024 · Proposed COD September 2028

200.58 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 5m

Facilities Study50%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

TX

County

Victoria

Region

ERCOT

Developer

Goldhill Energy Storage LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 8154 VISTRON4B _x0013_ 8189 TUNGSTEN4A

Data Source

LBNL + Live

No news available for this project.