Bologna BESS
BetaActiveBatteryERCOTLBNL + Live
202.56 MW storage in Wichita, TX · In queue since March 2024 · Proposed COD April 2028
202.56 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Facilities Study50%
Queue EntryMar 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-19
Project Details
State
TX
County
Wichita
Region
ERCOT
Developer
MALONEY BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend
Data Source
LBNL + Live
No news available for this project.