Ceres BESS
BetaActiveBatteryERCOTLBNL + Live
202.7 MW storage in Hunt, TX · In queue since October 2024 · Proposed COD November 2027
202.7 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Facilities Study50%
Queue EntryOct 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-30
Project Details
State
TX
County
Hunt
Region
ERCOT
Developer
Ceres BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS
Data Source
LBNL + Live