Ceres BESS — Project Summary

Queue ID
ERCOT-26INR0464
Capacity
202.7 MW
Technology
Battery
Status
active
Location
Hunt, TX
Region
ERCOT
Developer
Ceres BESS, LLC
IA Status
Facility Study

Ceres BESS

BetaActiveBatteryERCOTLBNL + Live

202.7 MW storage in Hunt, TX · In queue since October 2024 · Proposed COD November 2027

202.7 MW

Capacity

1

Components

Battery

1y 5m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

Facilities Study50%
Queue EntryOct 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-30

Project Details

State

TX

County

Hunt

Region

ERCOT

Developer

Ceres BESS, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS

Data Source

LBNL + Live