Dove Creek Solar
BetaActiveSolarERCOTLBNL + Live
163.6 MW generation in Tom Green, TX · In queue since July 2024 · Proposed COD July 2028
163.6 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntryJul 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Tom Green
Region
ERCOT
Developer
Dove Creek Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap at Big Hill - Twin Buttes 345 kV line (76003 / 76009)
Data Source
LBNL + Live
No news available for this project.